Serving O'Brien & Clay Counties

Milestones reached in H-M-S facilities project

Additional repairs needed to prevent water damage to high school

The construction, renovation and removal phases of the Hartley-Melvin-Sanborn Community School District's facilities project are reaching important milestones as the 2020-21 school year approaches.

According to project manager Mark Pfister, of Boyd Jones, the interior punch list for the elementary school phase of the project is ready to be reviewed. The list documents items that must be completed by the contractors in order to meet project specifications.

The fire marshal will also inspect the building to determine if all systems meet requirements. Pfister said the final concrete pour is sched...

 
 
Rendered 11/09/2024 06:00